Company or firm · first RERA registration 2018
Diwali Developers
Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 23 mo late.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay23 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Registration revoked | Vardhman PearlRegistration revoked / ab initio void: VARDHMAN PEARL | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vardhman VatikaP51700018906 | Thane (M Corp.) | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 mo |
| Vardhman PearlP51800032809 | Borivali | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +22 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology