Individual promoter · first RERA registration 2017
Dilip Dharmaji Wavhal
Deedo IDDD-22YCOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 16 mo late.
Projects12 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay16 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Devaki ComplexP52100009441 | Alefata (N.V.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Devaki ComplexP52100027738 | Alefata (N.V.) | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | +16 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology