Individual promoter · first RERA registration 2020
Dhiraj Narayandas Jadhwani
Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 8 mo — longer than Maharashtra's 4 mo.
Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay8 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 3 moved past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dj AmoreP51800026915 | Kurla | Certificate Signed | 5 Oct 2023 | 5 Oct 2023 | On date |
| Dj Amore2P51800048275 | Kurla | Certificate Signed | 1 Apr 2025 | 31 Mar 2026 | +11 mo |
| D J NestP51800049265 | Wadhavali | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology