Company or firm · first RERA registration 2017
Devi Infraspace Private Limited
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.
Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay18 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | Devis PlatinumComplaint CC002000000000040 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Devi HeavenP50300002482 | Amravati (M Corp.) | Certificate Signed | 31 Aug 2019 | 31 Aug 2019 | On date |
| Devis PlatinumP50300015308 | Amravati (M Corp.) | Completed | 30 Sep 2020 | 30 Mar 2022 | +18 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology