Company or firm · first RERA registration 2017
Dev Land & Housing Private Limited
Deedo IDDD-T55MOf 5 registrations whose promised date has arrived, 3 kept it (60%). The rest ran a median 18 mo late.
Projects66 RERA registrations
Kept RERA date60%Maharashtra: 73%
Median delay18 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 6 ran past the RERA date
Months late against the original RERA promise, per registration
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dev AshokaP51700003374 | Thane (M Corp.) | Certificate Signed | 31 May 2019 | 30 Nov 2020 | +89 mo* |
| Dlh OrnateP51800003604 | Andheri | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Dlh MetroviewP51800005170 | Andheri | Certificate Signed | 30 Apr 2018 | 30 Apr 2018 | On date |
| Dlh Dream TowerP51800006778 | Andheri | Certificate Signed | 30 Sep 2019 | 29 Mar 2021 | +18 mo |
| Dlh LegacyP51800033074 | Andheri | Certificate Signed | 31 Mar 2024 | 31 Mar 2024 | On date |
| Dlh DawnP51800054960 | Bandra | Certificate Signed | 31 Jan 2027 | 31 May 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology