Of 5 registrations whose promised date has arrived, 3 kept it (60%). The rest ran a median 18 mo late.

Projects66 RERA registrations
Kept RERA date60%Maharashtra: 73%
Median delay18 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 6 ran past the RERA date

Months late against the original RERA promise, per registration

6 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Dev AshokaP51700003374Thane (M Corp.)Certificate Signed31 May 201930 Nov 2020+89 mo*
Dlh OrnateP51800003604AndheriCertificate Signed31 Dec 201831 Dec 2018On date
Dlh MetroviewP51800005170AndheriCertificate Signed30 Apr 201830 Apr 2018On date
Dlh Dream TowerP51800006778AndheriCertificate Signed30 Sep 201929 Mar 2021+18 mo
Dlh LegacyP51800033074AndheriCertificate Signed31 Mar 202431 Mar 2024On date
Dlh DawnP51800054960BandraCertificate Signed31 Jan 202731 May 2027+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology