Dadamiya Infrastructure Llp

None of 3 registrations has reached its promised completion date yet.

Projects33 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Dadamiyas EmeraldP51800056273KurlaCertificate Signed31 Mar 202731 Mar 2027On date
Ambrose HeightsP51800056407KandivaliCertificate Signed31 Mar 202731 Jul 2027+4 mo
Dadamiya’s Man'souza HeightPR1180002601930KurlaCertificate Signed31 Mar 202831 Mar 2028On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology