Company or firm · first RERA registration 2017
Consortexe Properties Pvt Ltd
Of 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 4 mo late.
Projects46 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 6 ran past the RERA date
Months late against the original RERA promise, per registration
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Anandvan Dabholkar SankulP52900001575 | Pinguli | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Anandvan Dabholkar SankulP52900014584 | Pinguli | Certificate Signed | 30 Nov 2019 | 30 Nov 2019 | On date |
| Anandvan Dabholkar SankulP52900027528 | Pinguli | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | On date |
| Aarambh Business CentreP52900045789 | Pinguli | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | +40 mo* |
| Anandvan Sairaj Sankul Phase 1P52900046802 | Pinguli | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Tarangan B WingP52900076691 | Sangirde | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology