City Ethernal Llp

None of 6 registrations has reached its promised completion date yet.

Projects66 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
City Ethernal Llp developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

4 registrations of 6 moved past the RERA date

Months late against the original RERA promise, per registration

6 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
West ViewP52100078640GultekadiCertificate Signed30 Sep 202930 Jan 2030+4 mo
SarasnagarPR1260002500761Pune (M Corp.)Certificate Signed31 Dec 203031 Dec 2030On date
MayfairPR1260002500776Pune (M Corp.)Certificate Signed31 Dec 203030 Apr 2031+4 mo
White House APR1260002501620Pune (M Corp.)Certificate Signed28 Feb 203128 Feb 2031On date
White House BPC1260002501754YerawadaCertificate Signed28 Feb 203128 Jun 2031+4 mo
Sai TowersPR1260002502058ParvatiCertificate Signed1 Apr 20311 Aug 2031+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology