Company or firm · first RERA registration 2017

Chinnaiah Venkatesh Gowda

Deedo IDDD-1X3V

None of 3 registrations has reached its promised completion date yet.

Projects33 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Srushti Raj SiddhiP51800002790KurlaCertificate Signed25 Dec 202725 Apr 2028+4 mo
Srushtiraj TowerP51800009157KurlaCertificate Signed25 Dec 202625 Apr 2027+4 mo
Srushtiraj Siddhi SquareP51800054297ChemburActive30 Dec 2028—On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology