Chhadva Construction
Deedo IDDD-8JTHOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 82 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Chhadva PlatinumP52000015895 | Taloje Panchnad | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | +82 mo* |
Chhadva Construction, in questions
Does Chhadva Construction finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 82 mo late. Across Maharashtra, 73% kept their date.
How many projects has Chhadva Construction registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Chhadva Construction have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.