Charms Corporation

Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 58 mo late.

Projects23 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay58 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency

1 registration of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Charms Paradise C WingP51700004417TitwalaCertificate Signed31 Mar 201831 Mar 2018On date
Charms ParkP51700004476TitwalaCertificate Signed31 Mar 201831 Mar 2018On date
Charms ParkP51700004494TitwalaCertificate Signed30 Dec 202130 Dec 2021+58 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology