Company or firm · first RERA registration 2023
Charholi Infrastructure Llp
None of 4 registrations has reached its promised completion date yet.
Projects44 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
4 registrations of 4 moved past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Montreal - A-B-C-DP52100053279 | Charholi | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Rio TowerP52100055493 | Charholi | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Montreal - E-HP52100077138 | Charholi | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Montreal F-GPR1260002601380 | Charoli | Certificate Signed | 31 May 2031 | 30 Sep 2031 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology