Company or firm · first RERA registration 2017
Calyx Merlin Ventures Llp
Of 3 registrations whose promised date has arrived, 2 were never extended past it (67%).
Projects23 RERA registrations
Kept RERA date67%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 3 moved past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| PrakritiP52100000311 | Kasar Amboli | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| PrakritiP52100000312 | Kasar Amboli | Certificate Signed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| Nikunj NavyanganP52100000512 | Kasar Amboli | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology