Company or firm · first RERA registration 2017
Blackplinth Developers Llp
Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 83 mo — longer than Maharashtra's 4 mo.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay83 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 1 moved past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| H and M RoyalP51900011158 | Ward Fnorth | Certificate Signed | 27 Jan 2019 | 31 Dec 2025 | +83 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
