Company or firm · first RERA registration 2018

Bindra Sateri Constructions

Deedo IDDD-2TYV

Of 4 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 34 mo late.

Projects44 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay34 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

4 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Bindra Sateri Legacy C Wing And F Wing Phase I - Upto 10th FloorP51800017120AndheriCertificate Signed30 Dec 202229 Dec 2023+46 mo*
Sateri Legacy B Wing Phase I- 2nd and above floorsP51800024998AndheriCertificate Signed30 Dec 202330 Dec 2023+34 mo*
Bindra Sateri Legacy C Wing And F Wing Phase II - 11th And Above FloorsP51800025061AndheriCertificate Signed30 Dec 202330 Dec 2023+34 mo*
Bindra Legacy A wing Ground , 1st to 14th and above floorsP51800025063AndheriCertificate Signed30 Dec 202330 Dec 2023+34 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology