Company or firm · first RERA registration 2019

Bhosale Buildcon

Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%).

Projects33 RERA registrations
Kept RERA date0%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Bhosale Buildcon developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

3 registrations of 3 moved past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Bhosale PalashP52000022551WahalCertificate Signed28 Nov 202231 May 2024+18 mo
Bhosale BluestarP52000022662WahalCertificate Signed28 Aug 202230 Sep 2024+25 mo
SaichaitanyaP52000031098WahalCertificate Signed31 Dec 202630 Apr 2027+4 mo