Bholenath Developers Ltd

Of 4 registrations whose promised date has arrived, 1 were never extended past it (25%).

Projects44 RERA registrations
Kept RERA date25%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Bholenath Developers Ltd developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

3 registrations of 4 moved past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Ambaji Niketan Co-Op. Housing Society Ltd.P51800000759KurlaCertificate Signed30 Jun 201830 Dec 2020+30 mo
Zen ApartmentsP51800002227KurlaCertificate Signed31 Mar 201831 Mar 2018On date
Hresa - Sainagar Apartment Pvt. Ltd.P51800004835KurlaCertificate Signed14 Nov 202214 Nov 2023+12 mo
Aura Apartments - Phase 2 11th FloorP51800009179KurlaCertificate Signed31 Oct 201831 Dec 2023+62 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology