Bhagyashree Enterprises
Deedo IDDD-Q5AGNone of 2 registrations has reached its promised completion date yet.
Projects12 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Jai Malhar ApartmentPR1270002500639 | Shedung | Certificate Signed | 31 Jul 2028 | 30 Nov 2028 | +4 mo |
| Jai Malhar ApartmentPR1270002600269 | Shedung | Certificate Signed | 30 Sep 2028 | 30 Jan 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology