Company or firm · first RERA registration 2022

Bhagat Builders

Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Bhagat GalaxyP52100047469Talegaon Dabhade (M Cl)Certificate Signed31 Dec 202331 Dec 2023On date
Bhagat CrystalP52100051808MawalCertificate Signed31 Dec 202431 Dec 2024On date
Bhagat PridePM1260002501380Talegaon Dabhade (M Cl)Certificate Signed31 Dec 202830 Apr 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology