Bhagat Builders
Of 2 registrations whose promised date has arrived, 2 kept it (100%).
Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Bhagat GalaxyP52100047469 | Talegaon Dabhade (M Cl) | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | On date |
| Bhagat CrystalP52100051808 | Mawal | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Bhagat PridePM1260002501380 | Talegaon Dabhade (M Cl) | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology