Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).

Projects33 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Benjamin Michael Manuel developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

1 registration of 3 moved past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Blue Bells ParkP52100052185Pune (M Corp.)Certificate Signed31 Dec 202431 Dec 2024On date
Bliss EstatesP52100056088Lonavala (M Cl)Certificate Signed31 Dec 202630 Apr 2027+4 mo
Bliss Estates Phase 2PR1260002601713SadapurCertificate Signed31 Dec 202931 Dec 2029On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology