Bedekar Lifespaces Llp

Deedo IDDD-75K0

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late.

Projects44 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
BeezhiveP53000029433Kolhapur (M Corp.)Certificate Signed31 Dec 202531 Dec 2025On date
AravaliP53000034228Pachgaon (Ct)Certificate Signed31 Mar 202631 Jul 2026+7 mo*
EvanthaP53000054599KarvirCertificate Signed31 Dec 202730 Apr 2028+4 mo
Dhanashree SvastiP53000080005Kolhapur (M Corp.)Certificate Signed31 Dec 202830 Apr 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology