Company or firm · first RERA registration 2017

Beauty Ganraj Construction Llp

Of 2 registrations whose promised date has arrived, 2 were never extended past it (100%).

Projects22 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delayNonewhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases1no insolvency
Beauty Ganraj Construction Llp developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

No registration has been extended past its RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
complaintAureateComplaint CC006000000196733Not on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Beauty LandmarkP51800008233KurlaCertificate Signed31 Jul 201831 Jul 2018On date
AureateP51800023266KurlaActive30 Dec 2025—On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology