Company or firm · first RERA registration 2022
Beautiful Properties Private Limited
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Bhavesha Co-Operative Housing Society LtdP51800033264 | Andheri | Certificate Signed | 30 Nov 2023 | 30 Nov 2023 | On date |
| Commercial Wing - NL Plaza and Residential Wing - NL KrishnaP51800048076 | Borivali | Certificate Signed | 3 Aug 2026 | 3 Dec 2026 | +4 mo |
| Nl Park ViewP51800077375 | Kanheri | Certificate Signed | 30 May 2028 | 30 Sep 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology