Company or firm · first RERA registration 2023

Basil Avante Llp

Deedo IDDD-X48V

None of 5 registrations has reached its promised completion date yet.

Projects15 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

5 registrations of 5 ran past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Basil MaximusP52100050916PunawaleCertificate Signed31 Dec 202630 Apr 2027+4 mo
Basil MaximusP52100051323PunawaleCertificate Signed31 Dec 202730 Apr 2028+4 mo
Basil MaximusP52100056356PunawaleCertificate Signed31 Dec 202830 Apr 2029+4 mo
Basil MaximusP52100080092PunawaleCertificate Signed31 Dec 202930 Apr 2030+4 mo
Basil MaximusPR1260002503019PunawaleCertificate Signed31 Dec 202930 Apr 2030+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology