Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 18 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay18 mowhen late
Flats sold, all time1registered sale deeds
Regulatory cases0none on record

1 registration of 1 ran past the RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Neel GalaxyP52100045315HadapsarCertificate Signed21 Apr 202531 Dec 2025+18 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology