Individual promoter · first RERA registration 2017

Balasaheb Vyankatrao Gaikwad

Deedo IDDD-TBA2

Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects22 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

No registration has run past its RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Emerald ParkP52100001532PunawaleCertificate Signed30 Dec 202330 Dec 2023On date
Emerald Park B BuildingP52100020362Pimpri Chinchawad (M Corp.)Certificate Signed30 Jul 202230 Jul 2022On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology