Individual promoter · first RERA registration 2020
Baban Anant Patil
Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 52 mo late.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay52 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ananatganga Housing Complex Antargat Sharadban ApartmentP53100024197 | Uran Islampur (M Cl) | Certificate Signed | 30 Dec 2020 | 30 Dec 2020 | +70 mo* |
| Anantganga Housingg Project Antargat Royal Stone ApartmentP53100032421 | Uran Islampur (M Cl) | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | +34 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology