Company or firm · first RERA registration 2019

Avishkar Arista Developers Llp

Deedo IDDD-50VG

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 5 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay5 mowhen late · Maharashtra: 4 mo
Flats sold, all time204registered sale deeds
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
The Platinum TowersP52100019881KharadiCertificate Signed15 Mar 202519 Aug 2025+5 mo

Avishkar Arista Developers Llp, in questions

Does Avishkar Arista Developers Llp finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.

How many projects has Avishkar Arista Developers Llp registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Avishkar Arista Developers Llp have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology