Skip to content
Company or firm · first RERA registration 2025

Avanish Realty LLP

Deedo IDDD-87P8

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Avanish RoyalePR1180002500407KondivitaCertificate Signed31 Oct 202828 Feb 2029+4 mo

Avanish Realty LLP, in questions

Does Avanish Realty LLP finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has Avanish Realty LLP registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Avanish Realty LLP have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology