Individual promoter · first RERA registration 2017

Atul Arvind Bhosle

Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 8 mo — longer than Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay8 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Atul Arvind Bhosle developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

2 registrations of 3 moved past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Aditya PristineP52100001573BanerCertificate Signed31 May 201830 Apr 2019+11 mo
Aditya GalaxyP52100034834Pune CityCertificate Signed1 Apr 20251 Apr 2025On date
Aditya ShubhamPR1260002600881Kothrud-ExtCertificate Signed31 Mar 203031 Jul 2030+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology