Company or firm · first RERA registration 2018
Ashtavinayak Developers
Deedo IDDD-E19XOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 69 mo late — longer than Maharashtra's 4 mo.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay69 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
1 registration of 1 ran past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Jamtha GalaxyRegulatory order: PROJECT NAME:JAMTHA GALAXY (Regulatory Case No. 254 OF 2024) dated 02 July 2024. | 2 Jul 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Jamtha GalaxyP50500015383 | Jamtha | Active | 30 Mar 2023 | 31 Dec 2028 | +69 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology