Ashoka Township (Aop)

Deedo IDDD-FM7Z

Of 5 registrations whose promised date has arrived, 3 kept it (60%). The rest ran a median 29 mo late.

Projects35 RERA registrations
Kept RERA date60%Maharashtra: 73%
Median delay29 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 5 ran past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
TulipP51600005667NashikCompleted30 Jun 2019—On date
Gulmohar A, B, C BLDGSP51600009132SinnarCertificate Signed31 Dec 201831 Dec 2018On date
Neelmohar EP51600012230SinnarCertificate Signed31 Dec 202030 Jun 2022+18 mo
TulipP51600015179NashikCertificate Signed31 Dec 201931 Dec 2019On date
TulipP51600025442NashikCertificate Signed30 Jun 202330 Jun 2023+40 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology