Individual promoter · first RERA registration 2018
Ashish Anil Patil
Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.
Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay18 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Akruti KonarkP99000018993 | Palghar | Certificate Signed | 30 Oct 2020 | 30 Apr 2022 | +18 mo |
| Akruti Prime SquareP99000028675 | Mahim | Certificate Signed | 30 Jun 2023 | 31 Dec 2026 | +42 mo |
| Akruti HeavenP99000055094 | Palghar | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology