Ashish Anil Patil

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay18 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Akruti KonarkP99000018993PalgharCertificate Signed30 Oct 202030 Apr 2022+18 mo
Akruti Prime SquareP99000028675MahimCertificate Signed30 Jun 202331 Dec 2026+42 mo
Akruti HeavenP99000055094PalgharCertificate Signed31 Mar 202831 Jul 2028+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology