Of 8 registrations whose promised date has arrived, 4 kept it (50%). The rest ran a median 10 mo late.

Projects99 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay10 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

5 registrations of 9 ran past the RERA date

Months late against the original RERA promise, per registration

9 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Jayshree Apartments Phase IP52100005789Pune (M Corp.)Certificate Signed31 Dec 201831 Dec 2018On date
Mohan Apartment Phase IP52100019812Pune CityCertificate Signed30 Sep 202230 Sep 2022On date
Sunand Apartment Phase IP52100021064Pune CityCertificate Signed30 Dec 202230 Dec 2022On date
Leela ApartmentP52100034665Pune (M Corp.)Certificate Signed31 Mar 202431 Mar 2024On date
Sahil Co.op. Housing SocietyP52100047922Pune (M Corp.)Certificate Signed31 Dec 202431 Dec 2025+12 mo
Civcon ResidencyP52100049996Pune (M Corp.)Certificate Signed31 Dec 202431 Aug 2025+22 mo*
AnandP52100050190Pune (M Corp.)Certificate Signed30 Dec 202530 Dec 2025+10 mo*
Harshad ApartmentP52100052035Pune (M Corp.)Certificate Signed31 May 202630 Sep 2026+5 mo*
Marwa ApartmentsP52100079404Pune (M Corp.)Certificate Signed31 Dec 202830 Apr 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology