Of 3 registrations whose promised date has arrived, 3 were never extended past it (100%).

Projects99 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Ara Habitats Llp developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

No registration has been extended past its RERA date

Months late against the original RERA promise, per registration

9 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Mahalaxmi Nagar 24 Sector 1P50500046355JamthaCertificate Signed14 Jun 202614 Jun 2026On date
Mahalaxmi Nagar 24 Sector 3P50500046358JamthaCertificate Signed14 Jun 202614 Jun 2026On date
Mahalaxmi Nagar 24 Sector 2P50500046407JamthaCertificate Signed14 Jun 202614 Jun 2026On date
Mahalaxmi Nagar 28 Sector - 2P50500047463SondaparCertificate Signed20 Oct 202820 Oct 2028On date
Mahalaxmi Nagar 28 Sector - 1P50500047584SondaparCertificate Signed20 Oct 202820 Oct 2028On date
Mahalaxmi Nagar 33 Sector - 1P50500053637JamthaCertificate Signed25 Nov 202825 Nov 2028On date
Mahalaxmi Nagar 32P50500053785JamthaCertificate Signed25 Nov 202825 Nov 2028On date
Mahalaxmi Nagar 33 Sector - 3P50500053956JamthaCertificate Signed27 Dec 202827 Dec 2028On date
Mahalaxmi Nagar 33 Sector - 2P50500053962JamthaCertificate Signed12 Dec 202812 Dec 2028On date