Company or firm · first RERA registration 2017

Anmol Developers

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 9 mo late — longer than Maharashtra's 4 mo.

Projects12 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay9 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
The NatureP52000004480VanjaleCertificate Signed30 Dec 202330 Dec 2023On date
The NatureP52000034215VanjaleCertificate Signed30 Jun 202431 Mar 2025+9 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology