Company or firm · first RERA registration 2025

Ananta Sb Developers

Deedo IDDD-1Q98

None of 2 registrations has reached its promised completion date yet.

Projects12 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Siddhivinayak ApartmentP99000079008KapaseCertificate Signed31 Dec 202630 Apr 2027+4 mo
Siddhivinayak ApartmentPM1240002602322KapaseNot on record31 Mar 2029—On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology