Individual promoter · first RERA registration 2019
Anandkumar Baban Rajmane
Deedo IDDD-TD9BOf 6 registrations whose promised date has arrived, 5 kept it (83%). The rest ran a median 10 mo late.
Projects66 RERA registrations
Kept RERA date83%Maharashtra: 73%
Median delay10 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 6 ran past the RERA date
Months late against the original RERA promise, per registration
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Venkatesh RudraP53100019119 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 30 Mar 2022 | 30 Mar 2022 | On date |
| Venkatesh KasturiP53100019871 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | On date |
| Venkatesh WidijaP53100023049 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 25 Oct 2023 | 25 Oct 2023 | On date |
| Ventakesh TulsiP53100028048 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 25 Dec 2024 | 25 Dec 2024 | On date |
| Venkatesh MahalaxmiP53100047254 | Miraj | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Venkatesh PrabhaP53100048362 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +10 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology