Of 3 registrations whose promised date has arrived, 3 kept it (100%).

Projects13 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time49registered sale deeds
Regulatory cases0none on record

No registration has run past its RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Green CountyP52100004407FursungiCertificate Signed30 Dec 202230 Dec 2022On date
Green CountyP52100011772FursungiCertificate Signed31 Dec 201831 Dec 2018On date
Green CountyP52100026716FursungiCertificate Signed30 Jun 202530 Jun 2025On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology