Amit Vastu Ventures Llp

Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 30 mo — longer than Maharashtra's 4 mo.

Projects12 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay30 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Amit Vastu Ventures Llp developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

1 registration of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
MontecitoP52100002014ParvatiCertificate Signed30 Jun 201930 Dec 2021+30 mo
MontecitoP52100008717ParvatiCertificate Signed31 Dec 201831 Dec 2018On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology