Company or firm · first RERA registration 2017
Ami Estates LLP
Deedo IDDD-YZDFOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 7 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay7 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases2no insolvency
1 registration of 1 ran past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | VertillasRegulatory order: PROJECT NAME: VERTILLAS (Regulatory Case No. 400 OF 2025) dated 14 Oct, 2025. | 14 Oct 2025 |
| Regulatory order | VertillasRegulatory order: PROJECT NAME:VERTILLAS (Regulatory Case No. 256 OF 2024) dated 02 July 2024. | 2 Jul 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| VertillasP52100012616 | Haveli | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | +7 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
