Company or firm · first RERA registration 2017
Ameya Builders & Property Developers
Deedo IDDD-Y5SHOf 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 36 mo late — longer than Maharashtra's 4 mo.
Projects55 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay36 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
4 registrations of 5 ran past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Bldg No-16 VioletP99000002573 | Vasaivirar City (M Corp) | Certificate Signed | 31 Mar 2018 | 30 Mar 2022 | +48 mo |
| Bldg No-3 RoseP99000008563 | Vasaivirar City (M Corp) | Certificate Signed | 31 Mar 2018 | 30 Mar 2022 | +48 mo |
| Yashwant PrideP99000020925 | Vasaivirar City (M Corp) | Certificate Signed | 31 Mar 2020 | 30 Mar 2022 | +24 mo |
| Bldg No 1P99000046786 | Vasaivirar City (M Corp) | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Bldg No 23 Blue BellP99000053880 | Vasaivirar City (M Corp) | Certificate Signed | 31 Dec 2028 | 31 Dec 2028 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology