Individual promoter · first RERA registration 2021
Ajinkya Tushar More
Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.
Projects44 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 4 ran past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Riddhi Siddhi AppartmentP53100028168 | Vita (M Cl) | Certificate Signed | 30 Jun 2027 | 30 Jun 2027 | On date |
| Riddhi Siddhi HeightsP52700031147 | Dahivadi | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Samruddhi AppartmentP53100047795 | Vita (M Cl) | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +10 mo* |
| Riddhi Siddhi ComplexP53100079690 | Vita (M Cl) | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology