Individual promoter · first RERA registration 2021
Aditya Developers Through Proprietor Kumar Balasaheb Chavan
Of 3 registrations whose promised date has arrived, 3 were never extended past it (100%).
Projects55 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 5 moved past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| KrishnadhamP52700031177 | Kodoli (Ct) | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Arihant ResidencyP52700034591 | Kodoli (Ct) | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
| Surekha CornerP52700049430 | Kodoli (Ct) | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | On date |
| Jagtap PlazaP52700079078 | Satara | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Jagdale GreensP52700079894 | Satara | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology