Company or firm · first RERA registration 2025
Abi Builders
Of 1 registration whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 4 mo — the same as Maharashtra's 4 mo.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 1 moved past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Rdm Elite - KissanP53000079671 | Karvir | Certificate Signed | 31 May 2026 | 30 Sep 2026 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
