Individual promoter · first RERA registration 2017
Abhay Indrabhan Fulfagar
Of 3 registrations whose promised date has arrived, 3 kept it (100%).
Projects24 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
No registration has run past its RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Revell OrchidP52100001549 | Haveli | Certificate Signed | 6 Jun 2022 | 6 Jun 2022 | On date |
| Revell OrchidP52100001922 | Haveli | Certificate Signed | 6 Dec 2019 | 6 Dec 2019 | On date |
| Revell OrchidP52100015949 | Haveli | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Revell Orchid Phase V Building GP52100034702 | Lohgaon | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology