Pick up to four MahaRERA-registered projects to see their delivery, registered prices, sales and regulatory record next to each other.

Projects compared side by side
Suraj Homes · Wahal
Delivery
Status3 yrs 3 mo late
Promised → actualJun 2023 → still open
Extension certificates1
Size & sales
Units booked10 / 20 · 50%
Buildings · land1 · —
Registration
RERA numbers
Status on MahaRERACertificate Signed
Registered on6 Oct 2020
Regulatory
MahaRERA cases0
Documents on file2
Last checked on MahaRERA12 Oct 2026

✓ marks the best value only where “best” is unambiguous. Prices are not ranked; medians need at least 3 registered deeds.