Skip to content

Compare

Compare projects side by side

Pick up to four MahaRERA-registered projects to see their delivery, registered prices, sales and regulatory record next to each other.

Projects compared side by side
Abhishek Dattatraya Malode · Nashik
Delivery
Status1 yr 8 mo late
Promised → actualJan 2025 → still open
Extension certificates0
Size & sales
Units bookedNot on record
Buildings · land1 · —
Registration
RERA numbers
Status on MahaRERACertificate Signed
Registered on4 Apr 2022
Regulatory
MahaRERA cases0
Documents on file1
Last checked on MahaRERA13 Oct 2026

✓ marks the best value only where “best” is unambiguous. Prices are not ranked; medians need at least 3 registered deeds.

Add a second

Add at least one more project to see which values are better.

Data through13 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders, project pages; registered documents (Index II) for pricesDelay counts months from the completion date promised at registration.Methodology