Skip to content
Deedo home
Menu

Vijay Sunstone

Completed

Bhandara (M Cl), Bhandara 441904 |Promoter: V Y Nikhar & Associates

Residential / Group HousingRERAP50600008375
18 Aug 2017Registered with MahaRERA
30 Dec 2022Promised completion
1Building
34Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
Flatstype1, Flatstype2, Flatstype3, Flatstype4, Flatstype5, Flatstype6, Flatstype7, Shops type 1, Shopstype2, Shopstype3, Shopstype434 units in all
Land area for this project
723 sq m (7,784 sq ft)
Permissible built-up area
1,443 sq m (15,534 sq ft)
Sanctioned built-up area
1,443 sq m (15,534 sq ft)
Address
Sheet No 38, Mouza BhandaraPIN 441904
Designated bank account
Union Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.16839, 79.65614
Vijay Sunstone is at latitude 21.16839, longitude 79.65614.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2022

The latest completion date on record passed 3 years and 10 months ago.

Registered
18 Aug 2017
Promised
30 Dec 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5060000837518 Aug 201730 Dec 2022—V Y Nikhar & AssociatesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Vijay Sunstone634

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

34 units registered

Flatstype1 · 2 unitsFlatstype2 · 2 unitsFlatstype3 · 4 unitsFlatstype4 · 4 unitsFlatstype5 · 2 unitsFlatstype6 · 4 unitsFlatstype7 · 1 unitShops type 1 · 12 unitsShopstype2 · 1 unitShopstype3 · 1 unitShopstype4 · 1 unit
TypeCarpet areaUnits
Flatstype154.56 sq m · 587 sq ft2
Flatstype250.85 sq m · 547 sq ft2
Flatstype353 sq m · 570 sq ft4
Flatstype454.56 sq m · 587 sq ft4
Flatstype586.57 sq m · 932 sq ft2
Flatstype653.02 sq m · 571 sq ft4
Flatstype738.98 sq m · 420 sq ft1
Shops type 119.36 sq m · 208 sq ft12
Shopstype222.44 sq m · 242 sq ft1
Shopstype316 sq m · 172 sq ft1
Shopstype410.23 sq m · 110 sq ft1

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00001

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Vijay Sunstone

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBOREWELL DONE10%
  • Sewerage (Chamber, Lines, Septic Tank , STP)TO BE PROVIDED EXCLUDING STP40%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalTO BE PROVIDED0%
  • Water conservation /Rain water harvestingTO BE PROVIDED0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

27 documents held by Deedo, 34 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Copy of the legal title report-Title Search Report.pdf · uploaded 26 Jul 2017View
  • Building Plan Approval (IOD)Building Permission Letter.PDF · uploaded 26 Jul 2017View
  • Declaration in FORM B-Form B.pdf · uploaded 26 Jul 2017View
  • Details of encumbrancesEncumbrance.pdf · uploaded 27 Jul 2017View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 27 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Certificate.pdf · uploaded 28 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)Building Permission Letter.PDF · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer.pdf · uploaded 22 Mar 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect.pdf · uploaded 22 Mar 2018View
  • Commencement Certificates / NA Order for plotted developmentBuilding Permission Letter.PDF · uploaded 13 Apr 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Silica Arch.pdf · uploaded 14 May 2018View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Sunstone Engg.pdf · uploaded 14 May 2018View
  • Certificates of CA (Form 5)Sunstone Engg.pdf · uploaded 14 May 2018View
  • Status of Formation of Legal Entity (Society/Co Op etc.)NOT APPLICABLE.pdf · uploaded 14 May 2018View
  • Status of ConveyanceNOT APPLICABLE.pdf · uploaded 14 May 2018View
  • OtherNOT APPLICABLE.pdf · uploaded 14 May 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sunstone Arch.pdf · uploaded 3 Sep 2018View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Sunstone Engg.pdf · uploaded 3 Sep 2018View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Vijay Sunstone- Ar.pdf · uploaded 11 Feb 2019View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Vijay Sunstone- Engg-compressed.pdf · uploaded 11 Feb 2019View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sunstone Ar_compressed.pdf · uploaded 31 May 2019View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Sunstone En_compressed.pdf · uploaded 31 May 2019View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Sunstone Engg.pdf · uploaded 29 Nov 2019View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sunstone Arc.pdf · uploaded 29 Nov 2019View
  • Certificates of CA (Form 5)bs.pdf · uploaded 29 Nov 2019View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Balance Sheet.pdf · uploaded 14 Feb 2020View
  • Certificates of Architect (Form 4)Vijay Sunstone Form4.pdf · uploaded 21 Feb 2020View

Promoter documents

  • Legal Title report-Title Search Report.pdf · uploaded 26 Jul 2017View
  • Declaration Form B-Form B.pdf · uploaded 26 Jul 2017View

Technical documents

  • Building Plan ApprovalBuilding Permission Letter.PDFView
  • Layout ApprovalBuilding Permission Letter.PDFView

Other legal documents

  • OtherNOT APPLICABLE.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Bhandara (M Cl), Bhandara taluka

Survey, CTS, gat or plot numbers

SHEET NO 38

As published on MahaRERA's project page

SHEET NO 38, MOUZA BHANDARA

Boundaries

North
Late Purushottam Dalal House
South
Road
East
12 Ft Road
West
Bada Bazar Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShreya Nikhar—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology