Completion was pushed back 4 months, to Jan 2028; no MahaRERA orders on record; 0% of its units are booked.
Bid (M Cl), Beed 431122 · Promoter: Ajinkya Baburao Shirale
Completion was pushed back 4 months, to Jan 2028
- This projectRegistered 22 May 2024, completion promised 30 Sep 2027, revised to 30 Jan 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
6 buildings
Open a building to see every flat, floor by floor.
- ROW HOUSE 12 to 152 floors · 4 units0% booked
- ROW HOUSE 16 to 262 floors · 11 units0% booked
- ROW HOUSE 1 to 112 floors · 11 units0% booked
- ROW HOUSE 27 to 372 floors · 11 units0% booked
- ROW HOUSE 38 to 412 floors · 4 units0% booked
- ROW HOUSE 42 to 512 floors · 10 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52300056250
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52300056250 | 22 May 2024 | 30 Sep 2027 | 30 Jan 2028 | Ajinkya Baburao Shirale | Project page |
Documents79
1 document held by Deedo, 78 filings listed on MahaRERA's project page
Finance
Legal
Show all 79 documentsShow fewer documents
Migrated
- 1 CERSAI detailsCersai Details.pdf · uploaded 16 Mar 2024Source
- 1 Declaration about Commencement CertificateDeclaration Commencement.pdf · uploaded 1 Apr 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Wthout Fact Signed.pdf · uploaded 1 Apr 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDiclosure promoter.pdf · uploaded 1 Apr 2024Source
- 1 Proforma of Agreement for saleDraft Agreement.pdf · uploaded 1 Apr 2024Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 1 Apr 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about Separate Bank Account for real estate proiects.pdf · uploaded 1 Apr 2024Source
- 1 Deviation Report with respect to Allotment letterDeviation report allotmentt.pdf · uploaded 1 Apr 2024Source
- 1 Deviation Report with respect to model copy of AgreementDeviation report agreement.pdf · uploaded 1 Apr 2024Source
- 1 a Details of encumbrances concerned to FinanceSelf Declaration Regarding Encumbrance.pdf · uploaded 13 Apr 2024Source
- 1 b Details of encumbrances concerned to LegalSelf Declaration Regarding Encumbrance.pdf · uploaded 13 Apr 2024Source
- 1 Copy of Layout Approval (in case of layout)Layout 1-2.pdf · uploaded 13 Apr 2024Source
- 2 Copy of Layout Approval (in case of layout)Layout 3-4.pdf · uploaded 13 Apr 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentLayout 5-6.pdf · uploaded 13 Apr 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentLayout 7.pdf · uploaded 13 Apr 2024Source
- 1 Declaration in FORM BAjinkya Shirale Bond.pdf · uploaded 13 Apr 2024Source
- 1 Other – TechnicalAnnexure A old.pdf · uploaded 24 Apr 2024Source
- 2 a Details of encumbrances concerned to FinanceEncumbrance Finance - Legal.pdf · uploaded 9 May 2024Source
- 2 b Details of encumbrances concerned to LegalEncumbrance Finance - Legal.pdf · uploaded 9 May 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 as on 30-06-2024 signed.pdf · uploaded 29 Apr 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 as on 30-09-2024 signed.pdf · uploaded 29 Apr 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 as on 31-12-2024 signed.pdf · uploaded 29 Apr 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 as on 31-03-2025 signed.pdf · uploaded 29 Apr 2025Source
- 1 Disclosure of sold/ booked inventory30 June 24 Inventory.pdf · uploaded 29 Apr 2025Source
- 2 Disclosure of sold/ booked inventory30 Sep 24 Inventory.pdf · uploaded 29 Apr 2025Source
- 3 Disclosure of sold/ booked inventory31 Dec 24 Inventory.pdf · uploaded 29 Apr 2025Source
- 4 Disclosure of sold/ booked inventory31 March 25 Inventory.pdf · uploaded 29 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1.pdf · uploaded 5 May 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q2.pdf · uploaded 5 May 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q3.pdf · uploaded 5 May 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 Q4.pdf · uploaded 5 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q1.pdf · uploaded 5 May 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q2.pdf · uploaded 5 May 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q3.pdf · uploaded 5 May 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q4.pdf · uploaded 5 May 2025Source
- Form 1Form 1 Q1.pdf · uploaded 23 May 2025Source
- Form 1Form 1 Q2.pdf · uploaded 23 May 2025Source
- Form 2Form 2 Q2.pdf · uploaded 23 May 2025Source
- Form 3Form 3 as on Q2.pdf · uploaded 23 May 2025Source
- Disclosure of Sold and Booked Inventory30 Sep 24 Inventory.pdf · uploaded 23 May 2025Source
- Form 1Form 1 Q3.pdf · uploaded 23 May 2025Source
- Form 2Form 2 Q3.pdf · uploaded 23 May 2025Source
- Form 3Form 3 as on Q3.pdf · uploaded 23 May 2025Source
- Disclosure of Sold and Booked Inventory31 Dec 24 Inventory.pdf · uploaded 23 May 2025Source
- Form 1Form1 Q4.pdf · uploaded 23 May 2025Source
- Form 2Form 2 Q4.pdf · uploaded 23 May 2025Source
- Form 3Form 3 as on Q4.pdf · uploaded 23 May 2025Source
- Disclosure of Sold and Booked Inventory31 March 25 Inventory.pdf · uploaded 23 May 2025Source
- Form 5 (FY 2024-2025)Form 5.pdf · uploaded 30 Sep 2025Source
- Withdrawal Update Form 1Form1.pdf · uploaded 22 Dec 2025Source
- Withdrawal Update Form 2Form 2 Q1.pdf · uploaded 22 Dec 2025Source
- Withdrawal Update Form 3Form3.pdf · uploaded 22 Dec 2025Source
- Withdrawal Update Form 1Form1.pdf · uploaded 18 Jan 2026Source
- Withdrawal Update Form 2Form 2 Q1.pdf · uploaded 18 Jan 2026Source
- Withdrawal Update Form 3Form3.pdf · uploaded 18 Jan 2026Source
- Withdrawal Update Form 1Form1.pdf · uploaded 24 Apr 2026Source
- Withdrawal Update Form 2Form 2 Q1.pdf · uploaded 24 Apr 2026Source
- Withdrawal Update Form 3Form 3 signed.pdf · uploaded 24 Apr 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals3 to 27, Sry No 210 T Pingale H No 1-1-9423 Final Plot no 3 to 28
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- Row House51 units in all
- Address
- Sry No 210 T Pingale H No 1-1-9423 Final Plot no 3 to 28 and 3 to 27, Chartha Road near Kapilmuni mandir, Gopal Nagari Ankush Nagar BeedPIN 431122
- Village
- Bid (M Cl), Beed taluka
- Designated bank account
- 35
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No 1 and Plot No 2
- South
- 9 Mtr Wide Road and Land of Rusutm Aage
- East
- Land of Bhaskar Jogdand and 9 Mtr Wide Road
- West
- Kapilmuni Temple and and 9 Mtr Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking51 units
0 of 51 units booked (0%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| ROW HOUSE 12 to 15 | Row House | 83.69 sq m · 901 sq ft | 4 | 0 |
| ROW HOUSE 16 to 26 | Row House | 88.53 sq m · 953 sq ft | 11 | 0 |
| ROW HOUSE 1 to 11 | Row House | 75.53 sq m · 813 sq ft | 1 | 0 |
| ROW HOUSE 1 to 11 | Row House | 79.57 sq m · 856 sq ft | 1 | 0 |
| ROW HOUSE 1 to 11 | Row House | 83.07 sq m · 894 sq ft | 1 | 0 |
| ROW HOUSE 1 to 11 | Row House | 88.43 sq m · 952 sq ft | 1 | 0 |
| ROW HOUSE 1 to 11 | Row House | 89.89 sq m · 968 sq ft | 7 | 0 |
| ROW HOUSE 27 to 37 | Row House | 82.61 sq m · 889 sq ft | 11 | 0 |
Show all 16 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| ROW HOUSE 38 to 41 | Row House | 88.57 sq m · 953 sq ft | 4 | 0 |
| ROW HOUSE 42 to 51 | Row House | 56.58 sq m · 609 sq ft | 1 | 0 |
| ROW HOUSE 42 to 51 | Row House | 58.76 sq m · 632 sq ft | 1 | 0 |
| ROW HOUSE 42 to 51 | Row House | 71.69 sq m · 772 sq ft | 1 | 0 |
| ROW HOUSE 42 to 51 | Row House | 82.57 sq m · 889 sq ft | 1 | 0 |
| ROW HOUSE 42 to 51 | Row House | 84.93 sq m · 914 sq ft | 1 | 0 |
| ROW HOUSE 42 to 51 | Row House | 90.67 sq m · 976 sq ft | 4 | 0 |
| ROW HOUSE 42 to 51 | Row House | 92.57 sq m · 996 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Aniruddha Deshmukh | — |
| Chartered accountant | Jyoti Waghmode | — |
| Chartered accountant | Santosh P Amte | — |
| Engineer | Datta Raghunath Kharsade | — |
Source: MahaRERA project page. Contact details are not shown.